Load out the Gallaf 3 oil rig components at PTSC Vung Tau port

Overview

The project to load out the rig structure including the jacket and topside of the Gallaf 3 project at PTSC Vung Tau port with the weight of 2,500 Mt and 4,733 MT respectively.

In this project, with the transportation of 2 types of components with different weights, the number of equipment to be mobilized was calculated to be most suitable for each type of component

With a componants of 2,500 MT, Sarens experts calculated the plan and chose to use a total of 96 axles SPMT and 8 PPUs of Scheuerle, including 48 axles and 2 PPUs of Trungnam SMC combined with 48 axles and 6 PPUs of Sarens to participate in the load out.

Load out chân đế giàn khoan có trọng lượng 2.500 tấn.

Load out the rig jacket with a weight of 2,500 MT.

In particular, with super-sized and super-weight components up to 4,733 MT, it is necessary to mobilize up to 216 axles SPMT and 9 PPUs to load out. This can be considered as one of the projects with the most number of SPMT axle mobilized for 1 transportation in Vietnam up to the present time.

Load out the rig topside with weight up to 4,733 MT.

SMC's mission

SMC participates in the project as a subcontractor to supply equipment for Sarens with the number of equipment being 48 axles SPMT and 2 PPUs.

The equipment is gathered at the project before performing the work to serve the inspection, combination, etc. to ensure absolute safety and highest efficiency.

Scale

Location
PTSC Vung Tau port
Weigh
2,500MT and 4,733MT
Equipment
SPMT Scheuerle
Number of equipments mobilized
216 axles SPMT and 9 PPUs

Kinh nghiệm liên quan

Bộ đôi sà lan 14.000 tấn tham gia thay cánh dự án điện gió Đông Hải 1 - Trà Vinh
Replacing wind turbine blades at Dong Hai 1 – Tra Vinh project
See details
Thay cánh quạt điện gió
Replacing and repairing wind turbine blades of Phuong Mai wind power project – Binh Dinh
See details
Transporting Enercon E160 wind turbine blades from Ba Son port to Dak Lak
See details
Transporting wind power equipment from Nam Van Phong port to Dak Lak
See details
Load in the Goliath 700MT crane components at Hyundai Vietnam Shipbuilding
See details