Possessing the potential of transportation device and specialized construction capabilities, Trungnam SMC is currently one of the largest wind power project installers in Vietnam.

After a challenging 240 days and nights, the EaNam Dak Lak 1 wind power project was completed and officially put into commercial operation on October 31, 2021.

? The largest wind power project in Vietnam and a key project in Dak Lak province.

? Invested nearly 16,500 billion VND.

? Electricity output is 1.1 billion kWh/year.

? Capacity 400MW.

? Scale of 84 wind turbine.

 EaNam Dak Lak 1 wind power project

 

Onshore wind power projects directly constructed and installed by Trungnam SMC:

  • – Installing 84 wind turbine by 18 cranes of 800T – 1,250T type (EaNam Dak Lak Wind Power 1).
  • –  Installed 11 wind turbines with 3 800T crawler cranes, 3 180T crawler cranes, 1 220T wheel axle crane and 6 130T wheel axle cranes (No. 5 – Ninh Thuan Wind Power).
  • – Installed 45 wind turbine with 3 800T crawler cranes, 3 180T crawler cranes, 1 220T wheel axle crane and 6 130T wheel axle cranes (Trung Nam 1, 2, and 3 Wind Power).

Trungnam SMC will definitely be a reliable partner of customers in terms of construction and installation solutions for wind power.

CONTACT now with Trungnam SMC for the best advice and support!