Relocation of 350MT & 250MT jib cranes at Hyundai Vietnam Shipbuilding

Di dời cẩu bằng SPMT tại Hyundai Vietnam Shipbuilding

Overview

SMC directly organized the relocation of 2 super cranes Jib 350MT and Jib 250MT with their own weight of 2,950MT and 1,750MT, respectively at Hyundai Vietnam Shipbuilding.

For the transportation project at the HVS shipyard with narrow space characteristics, there are many obstacles that are ship modules being built and the passage is almost perpendicular, requiring the use of specialized equipment is SPMT to be able to do this job.

Di dời cẩu bằng SPMT tại Hyundai Vietnam Shipbuilding

SMC's mission

SMC has coordinated with HVS to unify and offer the best technical solutions before transportation.

SMC has also mobilized a technical team with many years of experience in trailer operation, including the direct consultation of leading experts in super-heavy transport from Europe of the Trungnam Group, mobilized a total of 144 SPMT axles and 8 PPUs of Scheuerle to carry out the relocation.

Đội ngũ vận hành SPMT của Trungnam SMC có nhiều năm kinh nghiệm và chuyên môn cao.

Scale

Location
Huyndai Vietnam Shipbuilding
Weigh
2,950 MT and 1,750 MT
Equipment
SPMT Scheuerle
Number of equipments mobilized
144 axle SPMT and 8 PPU

Kinh nghiệm liên quan

Bộ đôi sà lan 14.000 tấn tham gia thay cánh dự án điện gió Đông Hải 1 - Trà Vinh
Replacing wind turbine blades at Dong Hai 1 – Tra Vinh project
See details
Thay cánh quạt điện gió
Replacing and repairing wind turbine blades of Phuong Mai wind power project – Binh Dinh
See details
Load out the Gallaf 3 oil rig components at PTSC Vung Tau port
See details
Transporting Enercon E160 wind turbine blades from Ba Son port to Dak Lak
See details
Transporting wind power equipment from Nam Van Phong port to Dak Lak
See details